Type
Roadway Improvements
Project number
1082
Council Districts
01, 03, 05, 06, 09

Scope

Includes paving of unpaved portions of Braeburn Rd, Main St, Hirsch St, Ayr St, Newman Pl, Ford St, James Dr, and 5th St.

Paid

Project Start

Mar 2016

Design Finish

Construction Start

Apr 2024

Construction Finish

Jun 2025
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Preconstruction
Planning & Development
Procurement
Design
Construction
Construction
Complete
Complete

Additional Project Information