Whitehall St- 1.09 miles from Ralph David Abernathy Blvd to Memorial Dr - Scope of the project includes resurfacing of the project extents, roadway restriping to include protected bike lanes in both directions, and traffic signal upgrades to improve intersection safety.
Paid
0
Project Start
Jan 2024
Design Finish
Mar 2025
Construction Start
Jul 2025
Construction Finish
Oct 2026