West Paces Ferry Rd Resurfacing & Safety Improvements

Type
Street Repairs
Project number
4003
Council Districts
8

Scope

Complete resurfacing of the identified extents combined with safety improvements and interventions where feasible (e.g. vertical lane delineators/safe crossing treatments, lane narrowing, etc.) *Project should be considered for (in-house) mid-block crossing designs through corridor, as has been requested by community in the past. Consider other intersection related striping improvements as recommended in Tuxedo Park Transportation Study.

Paid

Project Start

Jun 2023

Design Finish

Construction Start

Jul 2023

Construction Finish

Mar 2025
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Not Started
Engineering/Design
Planning & Development
Procurement
Design
Construction
Construction
Closeout
Closeout

Additional Project Information

Project Videos