Scope

As a part of the Mayor’s Action Plan for Safer Streets, the project includes elements to improve safety for drivers, pedestrians, cyclists, wheelchair users, and scooter riders. Bicycle infrastructure improvements include protected bicycle lanes on West Peachtree St from Ponce de Leon to 16th St and on Spring St from 3rd St to 16th St.

Paid

Project Start

Sep 2018

Design Finish

Jun 2022

Construction Start

May 2025

Construction Finish

Nov 2026
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Planning/Scoping
Engineering/Design
Engineering/Design
Procurement
Procurement
Construction
Construction
Closeout
Closeout