Stafford St SW-Concrete Pavement Rehab

Type
Archive
Project number
1113
Council Districts
03, 04

Scope

Rehabilitation of concrete pavement, including improvements to an existing storm sewer drainage structure.

Paid

Project Start

May 2021

Design Finish

Construction Start

Nov 2021

Construction Finish

Jan 2022
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Preconstruction
Planning & Development
Procurement
Design
Construction
Construction
Complete
Complete

Additional Project Information