Type
Sidewalks
Project number
3054
Council Districts
04

Scope

Reconfigure a 0.29‐mile section of Peachtree Street between Trinity Ave and Alabama St from a 4‐lane section to a 2‐lane section. This will provide parallel parking spaces, widened sidewalks for pedestrian travel with ADA ramps, crosswalks at intersections, landscaping, seating areas, and pedestrian safety improvements. This project is in partnership with Atlanta Downtown Improvement District.

Paid

Project Start

Jul 2021

Design Finish

Nov 2026

Construction Start

Mar 2026

Construction Finish

Feb 2027
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Planning/Scoping
Engineering/Design
Engineering/Design
Procurement
Procurement
Construction
Construction
Closeout
Closeout

Additional Project Information