Sidney Marcus Blvd Safe Street & PATH 400 Link to Lindbergh MARTA Station

Type
Safe Streets
Project number
4132
Council Districts
6,7

Scope

Installation of improved pedestrian and bicycle facilities either in the form of on-street protected bike lanes or a side path, along with other safety improvements where feasible, along with resurfacing of the identified extents.

Paid

Project Start

Jan 2025

Design Finish

Mar 2027

Construction Start

Jun 2027

Construction Finish

Aug 2029
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Planning/Scoping
Engineering/Design
Engineering/Design
Procurement
Procurement
Construction
Construction
Closeout
Closeout

Additional Project Information