Piedmont Ave TCC Extension

Type
Project number
1062
Council Districts
06

Scope

PHASE 1 includes fiber optic cable installation and minor signal upgrades on Piedmont Ave between 14th and 15th St. PHASE 2 includes full signal upgrades (signal poles, controller cabinet, 4G communication, detection, pedestrian signals and push-buttons, ADA ramps, and signal timing improvements) at the intersection with The Prado NE (Botanical Garden entrance).

Paid

Project Start

Aug 2016

Design Finish

Construction Start

Jul 2024

Construction Finish

Jun 2026
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Preconstruction
Planning & Development
Procurement
Design
Construction
Construction
Complete
Complete