Type
Traffic Signals
Project number
1059
Council Districts
02, 03, 04, 06

Scope

Includes signal upgrades, fiber communications, and signal timing optimization from Memorial Dr to Spring St.

Paid

Project Start

Aug 2016

Design Finish

Aug 2022

Construction Start

Dec 2023

Construction Finish

Nov 2024
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning & Development
Planning & Development
Design
Design
Construction
Construction
Complete
Complete

Additional Project Information