Type
Archive
Project number
3016
Council Districts
07

Scope

Completing the final mile of connectivity along Peachtree Rd from Shadowlawn Ave to Maple Dr to existing bus stop and the Buckhead MARTA station. The project will include a typical section with three lanes in each direction with a raised landscape median. The project also includes new bicycle lanes, header curb, and a shoulder comprised of landscape strip and sidewalk on both sides of the roadway.

Paid

Project Start

Apr 2018

Design Finish

Nov 2019

Construction Start

Dec 2021

Construction Finish

Jul 2023
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Preconstruction
Planning & Development
Procurement
Design
Construction
Construction
Complete
Complete