Type
Multi-use Trails
Project number
1107
Council Districts
8

Scope

Includes a shared-use path connection that links Atlanta Memorial Park with the perimeter trail that goes around the Bobby Jones Golf Course. This connection would allow residents and trail users to safely cross Northside Drive by going underneath the new bridge being built by GDOT.

Paid

Project Start

Nov 2020

Design Finish

Jan 2021

Construction Start

Jul 2021

Construction Finish

Sep 2021
Disclaimer: Project schedules and scopes are subject to change.
0

Percent Complete

Phase

Not Started
Not Started
Planning & Development
Planning & Development
Design
Design
Construction
Construction
Complete
Complete