North Ave Complete Streets (Design-only)

Type
Archive
Project number
1014
Council Districts
02

Scope

Includes 60% design services for resurfacing, sidewalk repair, landscaping, curbing, ADA-compliant crosswalks and ramps, lighting, and traffic calming devices (where applicable) from Beltline East to Moreland Ave. Design will include bicycle infrastructure improvements at the BeltLine access point and in the uphill direction.

Paid

Project Start

Jan 2017

Design Finish

Construction Start

Construction Finish

Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Preconstruction
Planning & Development
Procurement
Design
Construction
Construction
Complete
Complete

Additional Project Information