Type
Sidewalks
Project number
4028
Council Districts
5

Scope

Repair & Installation of identified segments of missing sidewalk along corridor extents

Paid

Project Start

Mar 2024

Design Finish

Nov 2026

Construction Start

Feb 2027

Construction Finish

May 2028
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Not Started
Engineering/Design
Planning & Development
Procurement
Design
Construction
Construction
Closeout
Closeout

Additional Project Information