Type
Bridges
Project number
4040
Council Districts
9

Scope

Full replacement of the distressed and weight-limited bridge on Marietta Road over the CSX Tracks just South of Thomas St NW GDOT PI: 0019776 Legislation: 22-R-4179

Paid

Project Start

Apr 2024

Design Finish

Feb 2027

Construction Start

May 2027

Construction Finish

Aug 2029
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Not Started
Engineering/Design
Planning & Development
Procurement
Design
Construction
Construction
Closeout
Closeout

Additional Project Information