Type
Sidewalks
Project number
4117
Council Districts
10

Scope

Sidewalk installations to address missing segments along the corridor as identified by ATLDOT's Safety, Equity, and Mobility analysis.

Paid

Project Start

Jan 2025

Design Finish

Nov 2026

Construction Start

Feb 2027

Construction Finish

May 2028
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Planning/Scoping
Engineering/Design
Engineering/Design
Procurement
Procurement
Construction
Construction
Closeout
Closeout

Additional Project Information

Project Videos