Type
Sidewalks
Project number
3032
Council Districts
7

Scope

Provides pedestrian safety improvements and a shared-use trail along Lenox Rd between SR 141 (Peachtree Rd) and East Paces Ferry Rd, near the Lenox MARTA rail station.

Paid

Project Start

Aug 2018

Design Finish

Sep 2022

Construction Start

Dec 2023

Construction Finish

Nov 2024
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Preconstruction
Planning & Development
Procurement
Design
Construction
Construction
Complete
Complete

Additional Project Information