Installation of bicycle and pedestrian safety improvements where feasible ( e.g. ADA improvements, vertical lane delineators/safe crossing treatments, lane narrowing, etc.)
Paid
0
Project Start
Apr 2024
Design Finish
Sep 2026
Construction Start
Dec 2026
Construction Finish
Feb 2029