Type
Roadway Improvements
Project number
1108
Council Districts
6

Scope

Installation of a roundabout for roadway and mobility improvements at the intersection of Johnson Rd and Lenox Rd.

Paid

Project Start

Nov 2020

Design Finish

Feb 2024

Construction Start

Nov 2024

Construction Finish

Oct 2025
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning & Development
Planning & Development
Design
Design
Construction
Construction
Complete
Complete