Type
Safe Streets
Project number
1009
Council Districts
03, 04

Scope

Includes the rehabilitation of pavement, improvements to sidewalks and ADA ramps, installation of mid-block crossings with Rectangular Rapid Flashing Beacons (RRFB) at some locations and marked crosswalk at other locations, new Two-Way Left Turn Lanes, and Drainage improvements from Mitchell St to Joseph E Boone Blvd. Work also includes improvements to remove the traffic signal and re-align the intersection of Mayson Turner Rd, in addition to landscaping, pedestrian lighting and hardscaping to improve aesthetics. Signal coordination through fiber optic communication installation, and signal upgrades will also be implemented from MLK Blvd to Donald Lee Hollowell Pkwy.

Paid

Project Start

Aug 2015

Design Finish

Feb 2024

Construction Start

Mar 2024

Construction Finish

Feb 2027
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Preconstruction
Planning & Development
Procurement
Design
Construction
Construction
Complete
Complete