Type
Complete Street
Project number
1009
Council Districts
3, 4

Scope

Includes the rehabilitation of pavement, improvements to pedestrian infrastructure, installation of mid-block crossings, signal coordination, and signal upgrades from Mitchell St to Joseph E Boone Blvd. Work also includes improvements to re-align the intersection of Mayson Turner Rd, in addition to landscaping, streetlight and hardscaping to improve aesthetics. Signal upgrades will also be implemented on Mitchell St from Donald Lee Hollowell Pkwy.

Paid

Project Start

Aug 2015

Design Finish

Apr 2021

Construction Start

Jan 2022

Construction Finish

Dec 2022
Disclaimer: Project schedules and scopes are subject to change.
14

Percent Complete