Type
Archive
Project number
1074
Council Districts
01, 05

Scope

Includes the right-of-way acquisition for the realignment of SR 260/Glenwood Ave to the south to eliminate the approximate 70-foot offset that currently exists as it crosses US 23/SR 42/Moreland Ave. The realignment will accommodate two vehicular lanes and extend two bicycle lanes along Glenwood Ave through the Moreland Ave intersection. Glenwood Ave also will be restriped to accommodate a left-turn lane on the eastern leg of the intersection.

Paid

Project Start

Nov 2015

Design Finish

Construction Start

Jan 2018

Construction Finish

Jul 2019
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Planning/Scoping
Engineering/Design
Engineering/Design
Procurement
Procurement
Construction
Construction
Closeout
Closeout

Additional Project Information

Project Videos