Type
Sidewalks
Project number
4022
Council Districts
10,11

Scope

Addressing missing sidewalk segments on Fairburn Road from Hogan Rd SW to Alexandria Dr SW and from Kenner Dr SW to Thompson Dr NW (note the sidewalk from Kenner Dr SW to MLK Jr is covered by the Renew Fairburn Rd Improvements project# 1006)

Paid

Project Start

Feb 2024

Design Finish

Sep 2026

Construction Start

Dec 2026

Construction Finish

Mar 2028
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Not Started
Engineering/Design
Planning & Development
Procurement
Design
Construction
Construction
Closeout
Closeout

Additional Project Information