Eastside Trolley Greenway Trail

Type
Project number
1037
Council Districts
05

Scope

Includes the expansion of the Eastside Trolley Trail and shared-use path through the Reynoldstown, Edgewood, and Kirkwood neighborhoods from Stovall St to Arizona Ave.

Paid

Project Start

Sep 2019

Design Finish

May 2021

Construction Start

Jul 2022

Construction Finish

Oct 2023
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Preconstruction
Planning & Development
Procurement
Design
Construction
Construction
Complete
Complete