Type
Sidewalks
Project number
4029
Council Districts
6

Scope

Sidewalk installations to address missing segments along the corridor as identified by ATLDOT's Safety, Equity, and Mobility analysis.

Paid

Project Start

Mar 2024

Design Finish

Oct 2026

Construction Start

Jan 2027

Construction Finish

Apr 2028
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Planning/Scoping
Engineering/Design
Engineering/Design
Procurement
Procurement
Construction
Construction
Closeout
Closeout