Type
Safe Streets
Project number
4036
Council Districts
2,5

Scope

Central Park Pl - 0.77 miles from Baker-Highland Conn to SR 8 / US 19 / US 78 / US 278 / Ponce de Leon Ave - Scope of the project includes a resurfacing and restriping of Central Park Pl to include a protected bicycle lane in both directions and traffic signal upgrades to improve intersection safety.

Paid

Project Start

Jan 2024

Design Finish

Apr 2025

Construction Start

Aug 2025

Construction Finish

Nov 2026
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Planning/Scoping
Engineering/Design
Engineering/Design
Procurement
Procurement
Construction
Construction
Closeout
Closeout