Type
Archive
Project number
3025
Council Districts
11

Scope

Includes installation of new continuous sidewalk on the southside of Campbellton Rd from approximately 500 feet east of Dodson Dr to Bent Creek Way, on the northside of Campbellton Rd from approximately 500 feet west of Bent Creek Way to the westerly Wells Dr intersection, and from Sandringham Dr to approximately 500 feet east of Dodson Dr.

Paid

Project Start

Design Finish

Apr 2019

Construction Start

Sep 2019

Construction Finish

May 2020
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Planning/Scoping
Engineering/Design
Engineering/Design
Procurement
Procurement
Construction
Construction
Closeout
Closeout

Additional Project Information

Project Videos