Type
Safe Streets
Project number
1105
Council Districts
02, 05, 07, 08, 10, 11

Scope

Includes the construction of sidewalks along segments of Putman Drive, Old Ivy Rd, Hutchens Rd and University Avenue

Paid

Project Start

Jul 2020

Design Finish

Oct 2025

Construction Start

Sep 2026

Construction Finish

Jun 2027
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Planning/Scoping
Engineering/Design
Engineering/Design
Procurement
Procurement
Construction
Construction
Closeout
Closeout