Type
Sidewalks
Project number
4007
Council Districts
9

Scope

Sidewalk installations to address missing segments along the corridor as identified by ATLDOT's Safety, Equity, and Mobility analysis.

Paid

Project Start

Jul 2020

Design Finish

Mar 2026

Construction Start

Jun 2026

Construction Finish

Sep 2027
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Planning/Scoping
Engineering/Design
Engineering/Design
Procurement
Procurement
Construction
Construction
Closeout
Closeout

Additional Project Information

Project Videos