In case you missed it

Cheshire Bridge Partially Reopens in Each Direction

October 31, 2022

The Atlanta Department of Transportation is pleased to announce the partial reopening of Cheshire Bridge over South Fork Peachtree Creek. On Monday, October 31, 2022, crews opened one one northbound lane, one southbound lane and the west sidewalk of the bridge.  Mayor Andre Dickens, Councilmember Alex Wan, and community and business members joined ATLDOT Interim Commissioner Marsha Anderson-Bomar at the reopening to witness and commemorate this milestone of the rebuild project.

C. W. Matthews construction crews performed work both daily and nightly, to help accomplish the reopening as scheduled. The remaining lanes will be reopened in Spring 2023 following the completion of ongoing utility relocation work.

Click here for the full project update.

Link to WSB-TV

Associated Documents

Photos from the event

Questions or Comments?

Please contact us for questions or comments about this event.
Contact us