Scope

Includes the expansion of the PATH 400 shared-use path along SR 400 from Wieuca Rd to Loridans Dr, Loridans Dr to City Limits, and new segments within Peachtree Rd to Garson Dr.

Paid

Project Start

Dec 2018

Design Finish

Jun 2023

Construction Start

Nov 2022

Construction Finish

May 2025
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Preconstruction
Planning & Development
Procurement
Design
Construction
Construction
Complete