Type
Traffic Signals
Project number
3011
Council Districts
02, 06

Scope

Enhances existing street intersections to improve pedestrian mobility, safety, and connectivity from MARTA stations and numerous local, regional, and express bus stops within Midtown Core Boundary of the Midtown Community Improvement District (MCID).

Paid

Project Start

Dec 2016

Design Finish

Sep 2021

Construction Start

Feb 2022

Construction Finish

Jan 2023
Disclaimer: Project schedules and scopes are subject to change.