Type
Traffic Signals
Project number
3011
Council Districts
02,06

Scope

Enhances existing street intersections to improve pedestrian mobility, safety, and connectivity from MARTA stations and numerous local, regional, and express bus stops within Midtown Core Boundary of the Midtown Community Improvement District (MCID).

Paid

Project Start

Dec 2016

Design Finish

Aug 2021

Construction Start

Mar 2023

Construction Finish

May 2024
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning & Development
Planning & Development
Design
Design
Construction
Construction
Complete
Complete

Additional Project Information