Local District Sidewalk Additions

Type
Project number
1105
Council Districts
02, 05, 07, 08, 10, 11

Scope

Includes the construction of sidewalks along segments of Putman Drive, Old Ivy Rd, Beecher Rd, Hutchens Rd, University Avenue, and Peachtree-Dunwoody.

Paid

Project Start

Jul 2020

Design Finish

Construction Start

Apr 2025

Construction Finish

Jan 2026
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Preconstruction
Planning & Development
Procurement
Design
Construction
Construction
Complete