Type
Sidewalks & Mobility
Project number
1105
Council Districts
02, 05, 07, 08, 10, 11

Scope

Includes the construction of sidewalks along segments of Putman Drive, Old Ivy Rd, Beecher Rd, Hutchens Rd, University Avenue, and Peachtree-Dunwoody.

Paid

Project Start

Jul 2020

Design Finish

Dec 2022

Construction Start

Apr 2023

Construction Finish

Jan 2024
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning & Development
Planning & Development
Design
Design
Construction
Construction
Complete
Complete