Type
Sidewalks & Mobility
Project number
1105
Council Districts
02, 05, 07, 08, 10, 11

Scope

Includes the construction of sidewalks along Putman Drive (between Blackland Rd and Powers Ferry Rd), Old Ivy Rd, Beecher Rd and Hutchens Rd.

Paid

Project Start

Jul 2020

Design Finish

Sep 2022

Construction Start

Jan 2023

Construction Finish

Oct 2023
Disclaimer: Project schedules and scopes are subject to change.
0

Percent Complete

Phase

Not Started
Not Started
Planning & Development
Planning & Development
Design
Design
Construction
Construction
Complete
Complete