Scope

The project will install multimodal safety enhancements on Jackson St. and Parkway Dr between north of Highland Ave and John Wesley Dobbs Ave. Improvements include new pedestrian space, dedicated bike facilities, and upgraded ADA curb ramps. Additional work may include milling and inlay of asphalt and sidewalk repairs.

Paid

Project Start

Jan 2024

Design Finish

Construction Start

Jun 2025

Construction Finish

Sep 2025
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Planning/Scoping
Engineering/Design
Engineering/Design
Procurement
Procurement
Construction
Construction
Closeout
Closeout