Type
Archive
Project number
3042
Council Districts

Scope

Asphalt street resurfacing, milling, and point repairs; roadway striping, ADA-compliant ramp upgrades and installation; drainage, utility and other miscellaneous structure adjustments; and concrete work in the ROW at various locations throughout the City.

Paid

Project Start

Jan 2019

Design Finish

Construction Start

Sep 2021

Construction Finish

Dec 2021
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Preconstruction
Planning & Development
Procurement
Design
Construction
Construction
Complete
Complete

Additional Project Information