Type
Sidewalks & Mobility
Project number
3034
Council Districts
5

Scope

Includes new and expanded sidewalks, medians, lighting, tree plantings and other streetscape amenities, improved bus shelters, upgraded signalization, and additional turn lanes at intersections on Memorial Dr from Connally St to Grant St.

Paid

Project Start

Jan 2013

Design Finish

Jun 2025

Construction Start

Dec 2025

Construction Finish

Nov 2026
Disclaimer: Project schedules and scopes are subject to change.