RD Abernathy Blvd Complete Street

Archive

Type

Archive

Project Number

1018

Council Districts

04, 10

Scope

Includes the development of a high-level corridor vision for RD Abernathy Blvd, between Cascade Ave and Martin Luther King (MLK) Jr Dr, as well as a shared-use path and bicycle lanes for high-quality connection across MLK Jr Dr to the MARTA West Lake Station via Anderson Ave. Design and construction of this project is being coordinated with a GDOT resurfacing/restriping maintenance project. This project is in collaboration with Atlanta Beltline.

Current Budget

$1,500,000.00

Paid

$1199800.00
Project Start
2016-07-01

Anticipated Design Finish

2023-02-10

Construction Start

2023-12-08
Construction Finish
2024-10-31

Disclaimer: Project schedules and scopes are subject to change.