Scope

Includes design and construction of pedestrian improvements at North Ave and Somerset Terrace.

Paid

Project Start

Jun 2018

Design Finish

Aug 2020

Construction Start

Jun 2023

Construction Finish

May 2025
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning & Development
Planning & Development
Design
Design
Construction
Construction
Complete
Complete