Type
Roadway Improvements
Project number
1106
Council Districts
6

Scope

Includes replacement of striping with hardscape and possible Green Infrastructure and a separation of Montgomery Ferry Dr from the adjacent school driveway to provide a safer and better functioning intersection for pedestrian mobility and vehicular traffic flow.

Paid

Project Start

Sep 2020

Design Finish

Jul 2022

Construction Start

Dec 2022

Construction Finish

Nov 2023
Disclaimer: Project schedules and scopes are subject to change.
0

Percent Complete

Phase

Not Started
Not Started
Planning & Development
Planning & Development
Design
Design
Construction
Construction
Complete
Complete