Type
Traffic Signals
Project number
3040
Council Districts
2

Scope

Includes installation of new traffic signals on 13th St intersections at West Peachtree St, Peachtree St, and Juniper St. Bicycle signs and signals also will be installed.

Paid

Project Start

Jul 2017

Design Finish

Sep 2021

Construction Start

Feb 2023

Construction Finish

Feb 2024
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning & Development
Planning & Development
Design
Design
Construction
Construction
Complete
Complete