Type
Signals
Project number
3040
Council Districts

Scope

Includes installation of new traffic signals on 13th St intersections at West Peachtree St, Peachtree St, and Juniper St. Bicycle signs and signals also will be installed.

Paid

Project Start

Jul 2017

Design Finish

Construction Start

Mar 2023

Construction Finish

Mar 2024
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Preconstruction
Planning & Development
Procurement
Design
Construction
Construction
Complete
Complete

Additional Project Information