Scope

Includes resurfacing, restriping, new fiber communication between intersections, signals upgrades, partial corridor raised bicycle lanes, sidewalk repairs, additional mid-block crossings, 3 new signalized intersections, partial road diet, and ADA upgrades from Marietta St to Collier Rd.

Current Budget

$25,840,272.75

Paid

$11057785.08
Project Start
2016-01-15

Anticipated Design Finish

2021-07-31

Construction Start

2023-11-13
Construction Finish
2027-11-18