Type
Archive
Project number
1103
Council Districts
8

Scope

Includes the design and construction of 175 LF of sidewalk along Dudley Lane.

Paid

Project Start

Design Finish

Sep 2018

Construction Start

Oct 2018

Construction Finish

May 2019
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Not Started
Engineering/Design
Planning & Development
Procurement
Design
Construction
Construction
Closeout
Closeout

Additional Project Information

Project Videos