Ford Street NW from Spring Avenue NW to the Dead End Howell Mill Road from Trabert Avenue NW to Huff Road NW 10th Street NE from Piedmont Avenue NE to Monroe Drive NE Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Woodland Avenue SE from Lyndale Drive SE to Burn Street SE

Safe Streets

Downtown City Hall Vicinity Street Resurfacing

Archive

Type

Archive

Project Number

1123

Council Districts

04

Scope

Includes resurfacing and safety improvements along segments of Capitol Ave, Capitol Square, Central Ave, Martin Luther King Jr. Dr, Memorial Dr, Mitchell St, Trinity Ave, and Washington St. This project will incorporate design changes on the resurfaced streets in an effort to improve safety, particularly for vulnerable users such as pedestrians and bicyclists. The design supports the One Atlanta Strategic Transportation Plan for safer streets.

Current Budget

$6,444,962.28

Paid

$6444962.28
Project Start

Anticipated Design Finish

Construction Start

2022-11-19
Construction Finish
2023-08-31

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction