Type
Sidewalks
Project number
3031
Council Districts
8

Scope

Proposed widening of existing sidewalk on the Deering Road Bridge over I-75 between Loring Dr and Alden Ave.

Paid

Project Start

Dec 2019

Design Finish

Aug 2021

Construction Start

Mar 2025

Construction Finish

Apr 2025
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Not Started
Engineering/Design
Planning & Development
Procurement
Design
Construction
Construction
Closeout
Closeout

Additional Project Information

Project Videos