Type
Bridges
Project number
1020
Council Districts
01, 04

Scope

Includes bridge replacement from Martin Luther King (MLK) Jr Dr to Decatur St. Work includes new street and pedestrian lighting, repair of approaches, signal upgrades, and modification of curbing to create a full lane between Wall St and Decatur St.

Paid

Project Start

Oct 2016

Design Finish

Dec 2024

Construction Start

Aug 2025

Construction Finish

Aug 2027
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Preconstruction
Planning & Development
Procurement
Design
Construction
Construction
Complete
Complete