Campbellton Road Pedestrian Improvements

Sidewalks

Type

Sidewalks

Project Number

3030

Council Districts

11

Scope

Installation of new sidewalk pedestrian hybrid beacons (PHB) and other pedestrian mobility improvements in 6 intersections along Campbellton Rd at Star Mist Dr, Fire Station No. 5, Harbin Rd, Bent Creek Way, Wills Mill Dr, and Honeysuckle Ln.

Current Budget

$1,350,000.00

Paid

$244684.19
Project Start
2020-01-10

Anticipated Design Finish

2024-11-29

Construction Start

2026-04-07
Construction Finish
2026-04-07

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout