Installation of new sidewalk pedestrian hybrid beacons (PHB) and other pedestrian mobility improvements in 6 intersections along Campbellton Rd at Star Mist Dr, Fire Station No. 5, Harbin Rd, Bent Creek Way, Wills Mill Dr, and Honeysuckle Ln.
Paid
233492
Project Start
Jan 2020
Design Finish
Nov 2024
Construction Start
Aug 2025
Construction Finish
Mar 2026