Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW McLendon Avenue NE from Candler Street NE to Sterling Street NE Moores Mill Road NE & Ridgewood Road NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW McLendon Avenue NE from Candler Street NE to Sterling Street NE Moores Mill Road NE & Ridgewood Road NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW McLendon Avenue NE from Candler Street NE to Sterling Street NE Moores Mill Road NE & Ridgewood Road NW

Safe Streets

Campbellton Rd Complete Street

Safe Streets

Type

Safe Streets

Project Number

1001

Council Districts

11

Scope

DESIGN ONLY. Includes complete street and smart corridor design elements, which will improve the overall mobility, safety, and accessibility of the roadway for all users. The project extends from Enon Rd to Camp Ground Rd.

Current Budget

$11,258,649.30

Paid

$4246201.83
Project Start
2017-12-01

Anticipated Design Finish

2027-01-04

Construction Start

2027-04-22
Construction Finish
2028-04-07