Type
Project number
1001
Council Districts
11

Scope

DESIGN ONLY. Includes complete street and smart corridor design elements, which will improve the overall mobility, safety, and accessibility of the roadway for all users. The project extends from Enon Rd to Camp Ground Rd.

Paid

Project Start

Dec 2017

Design Finish

Construction Start

Apr 2026

Construction Finish

Apr 2028
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Preconstruction
Planning & Development
Procurement
Design
Construction
Construction
Complete
Complete