Improved signal operations throughout the Buckhead area using signal upgrades, including radar detection and traffic responsive signal timing. Also adding preemption for Fire and Rescue vehicles at various intersections.

Paid

Project Start

Sep 2018

Design Finish

Apr 2019

Construction Start

Aug 2025

Construction Finish

Nov 2025
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Not Started
Engineering/Design
Planning & Development
Procurement
Design
Construction
Construction
Closeout
Closeout