Includes bicycle, pedestrian, and multi-modal improvements along 1.5 miles of 5th St, from Williams St near Tech Square to Myrtle St in the Midtown Garden District. The project will replace damaged sidewalks and curbs; install curb extensions and bulb-outs; upgrade crosswalks as needed to be ADA-compliant; infill and replace pedestrian-scale lighting; infill and replace street trees; resurface and restripe roadway pavement; install a new traffic signal at Williams St & 5th St; and upgrade the existing bicycle facilities with high-quality connections (two-way cycle track on Tech Square) to the larger Midtown bicycle network.

Current Budget

$2,132,000.00

Paid

$2132000.00
Project Start
2018-05-01

Anticipated Design Finish

2021-07-31

Construction Start

2024-01-16
Construction Finish
2025-05-09

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout

No related events selected.

Scroll to Top