Jesse Hill, Jr., Drive SE from Decatur Street SE to Gilmer Street SE Noble Drive NE from Johnson Road NE to Meadowvale Avenue NE Ford Street NW from Spring Avenue NW to the Dead End Howell Mill Road from Trabert Avenue NW to Huff Road NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW

Safe Streets

2021 LMIG Resurfacing

Archive

Type

Archive

Project Number

3057

Council Districts

All

Scope

Asphalt street resurfacing, milling, and point repairs; roadway striping, ADA-compliant ramp upgrades and installation; drainage, utility and other miscellaneous structure adjustments; and concrete work in the ROW at various locations throughout the City.

Current Budget

$12,223,026.51

Paid

$12178025.94
Project Start
2022-01-01

Anticipated Design Finish

Construction Start

2023-07-31
Construction Finish
2024-09-30

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout