Type
Roadway Improvements
Project number
1072
Council Districts
02, 03

Scope

Includes the extension of 15th St two blocks westward from West Peachtree St to Williams St to improve traffic circulation for vehicles, bicycles, and pedestrians through the Midtown area.

Paid

Project Start

Nov 2016

Design Finish

Jan 2022

Construction Start

Feb 2024

Construction Finish

Sep 2025
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Planning/Scoping
Engineering/Design
Engineering/Design
Procurement
Procurement
Construction
Construction
Closeout
Closeout

Additional Project Information