McLendon Avenue NE from Candler Street NE to Sterling Street NE Moores Mill Road NE & Ridgewood Road NW McLendon Avenue NE from Candler Street NE to Sterling Street NE Moores Mill Road NE & Ridgewood Road NW McLendon Avenue NE from Candler Street NE to Sterling Street NE Moores Mill Road NE & Ridgewood Road NW

Safe Streets

AIM Fiber Comm Group

Archive

Type

Archive

Project Number

1046

Council Districts

02, 03, 04

Scope

Includes installation of fiber between City facilities and procuring the network integration equipment for the City’s Fiber network.

Current Budget

$1,313,303.45

Paid

$1313303.45
Project Start
2018-04-16
Anticipated Design Finish
2018-08-02

Construction Start

2018-10-01
Construction Finish
2020-01-31

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout